VDOT K34
Ashland, VA - Soil StabilizationSTART DATE:
February 2018
COMPLETION DATE:
March 2018
FINAL CONTRACT AMOUNT:
$42,360.96
CONTRACTOR:
Fielder’s Choice Enterprises
HOW WE OVERCAME, ORCHESTRATED OUTCOME:
K34 was a short soil stabilization project we performed for Fielder’s Choice Enterprises. We purchased lime from a Winchester, VA plant and used it to reacclimate the road they were working on.