UMW ANNEX B PARKING LOT
Fredericksburg, VA - Site Development & UtilitiesSTART DATE:
July 2017
COMPLETION DATE:
September 2017
FINAL CONTRACT AMOUNT:
$237,493.89
CONTRACTOR:
Donley’s
RISKS:
- Extremely tight deadline
- Occupied campus
- Interface with campus and tight neighborhood streets and traffic
- Abandoned foundations from previous buildings
HOW WE OVERCAME, ORCHESTRATED OUTCOME:
- Just in time export, import and material deliveries
- Off peak manhole and pipe deliveries
- Flagmen and specialty signage for traffic control
- Partial sidewalk closing