STONEY POINT FASHION PARK
Richmond, VA - Site Development & Stormwater ManagementSTART DATE:
August 2017
COMPLETION DATE:
December 2017
FINAL CONTRACT AMOUNT:
$316,080.93
CONTRACTOR:
Graycor
RISKS:
- Working inside the courtyard and occupied town center
HOW WE OVERCAME, ORCHESTRATED OUTCOME:
- Barricades
- Just in time delivery
- Small and specialty equipment
- Working off hours to export and import materials
- Using multiple crews in order to meet strict holiday deadlines