ROUTE 29 SOLUTIONS
Charlottesville, VA - Stormwater ManagementSTART DATE:
April 2016
COMPLETION DATE:
June 2017
FINAL CONTRACT AMOUNT:
$2,465,512.58
CONTRACTOR:
Lane Corman Construction
RISKS:
- Working in active stream beds
- Staying ahead of the 20’-30’ fills
- Working out of sequence to accommodate site access and schedule needs
HOW WE OVERCAME, ORCHESTRATED OUTCOME:
- We used twice the equipment in order to facilitate working on two side of the river
- We augmented crews as needed
- We used a dedicated backfill crew
- We used two utility crews when needed