VDOT I31 - CHESTERFIELD, VA – COURTHOUSE ROAD TURN LANE IMPROVEMENTS
START DATE:
March 2016
COMPLETION DATE:
March 2016
FINAL CONTRACT AMOUNT:
$80,950.28
CONTRACTOR:
S.B. Cox, Inc.
RISKS:
- Unsuitable soils
HOW WE OVERCAME, ORCHESTRATED OUTCOME:
Geotextile fabric and the import of granite dust as select fill so that the weather would not have adverse effects on the construction timeline