I395 EXPRESS LANES
Northern Virginia - Utility WorkSTART DATE:
July 2018
COMPLETION DATE:
October 2018
FINAL CONTRACT AMOUNT:
$426,396.84
CONTRACTOR:
Lane Construction
RISKS:
- The project involved setting structures and had to be performed during the night into the early morning, which made visibility difficult without proper lighting.
- The area around I395 where we were working was heavily congested all throughout the night.
- Limited work space due to working in the middle of I395. Could only bring machines of a limited size due to these restrictions.
- Critical utilities in the area.
HOW WE OVERCAME, ORCHESTRATED OUTCOME:
- Our crew was self-sufficient by bringing their own lighting and tools.