COVE POINT DOSWELL - DOSWELL, VA – GRADING & STONE FOR STORAGE YARD
START DATE:
January 2016
COMPLETION DATE:
February 2016
FINAL CONTRACT AMOUNT:
$151,646.14
CONTRACTOR:
IHI/Kiewit
RISKS:
- Weather (snow)
- Extreme deadline
- Ground water and storm runoff
HOW WE OVERCAME, ORCHESTRATED OUTCOME:
We were hired to build a temporary laydown yard to support the Dominion Energy Natural Gas Facility. The conditions of the laydown yard were wet and soft and not suitable to support heavy loads. We began the project and were caught by substantial snow storms. In order to deliver on time, we pushed the snow off in shifts and worked 16 to 20 hours a day.