VDOT K34 Ashland, VA - Soil Stabilization START DATE: February 2018 COMPLETION DATE: March 2018 FINAL CONTRACT AMOUNT: $42,360.96 CONTRACTOR: Fielder’s Choice Enterprises HOW WE OVERCAME, ORCHESTRATED OUTCOME: K34 was a short soil stabilization project we performed...
OCEANA SOLAR PROJECT Virginia Beach, VA - Soil Stabilization START DATE: August 2017 COMPLETION DATE: September 2017 FINAL CONTRACT AMOUNT: $205,976.25 CONTRACTOR: Amec Foster Wheeler Kamtech RISKS: Working in a swamp HOW WE OVERCAME, ORCHESTRATED OUTCOME: Sheer will...